Project Description
Project information
The project involves the construction of a gravity sewer under the Boulevard de la Croisette in Cannes, as a part of the restructuring of sewage networks.
Project description
BESSAC completed the construction of the gravity sewer, 2,300 m long in 4 drives and
1,600 mm internal diameter using a MTBM:
- First drive: 326 m long,
- Second drive: 721 m long,
- Third drive: 575 m long,
- Fourth drive: 655 m long.
Owner :
CAPL Communauté d’Agglomération Cannes Pays de Lérins
Engineer :
SUEZ Consulting – SAFEGE
General contractor :
Consortium: BESSAC (Leader), NGE GC, RAZEL-BEC, EHTP, NGE Fondations.
Period of works :
August 2022 – June 2024

A project?